Approval of Grant Agreement between the Board of Commissioners and Indiana Department of Environmental Management for $5,000 Community Recycling Grant on behalf of the Allen County Department of Environmental Management.
Approval of Bid Award for Bid Ref # 10-2020 for the 2020 Community Crossing Matching Grant; to the lowest bidder E & B Paving, in the amount of $1,959,882.50.
Approval of Supplemental Agreement #1 between the Board of Commissioners and A & Z Engineering for Railroad Study for Webster Rd. and Gar Creek Rd. Intersection; in the amount of $67,450.00.
Receipt of Letter from Indiana Department of Transportation for unofficial detour for US 33 over Johnson Drain.
Approval of Change Order # 1 and Final for Bid Ref # 9-12, for 2019 Traffic Pavement Markings, Project # 0002719, in the amount of $6,180.60 (decrease).
Project Acceptance for Bid Ref # 9-12, for 2019 Traffic Pavement Markings, Project #0002719, in the final contract amount of $257,812.24.
Approval of claims in the amount of $889,505.11 for the period of June 3 to June 9, 2020.